Organization |
Energy & Environmental Protection, Department of |
Project/Solicitation # |
DEPA00029000104-DevilsHopyard |
Solicitation Type |
Request for Quote |
Due Date |
04/15/2020 |
Includes SBE/MBE Requirements |
NO |
Qualified Partnership |
NO |
Summary |
Superstructure Replacement of a Wooden Covered Bridge located in Devil’s Hopyard State Park. |
|
|
Addenda |
- Addendum #4 - As such, due to the change of the sealed bids submission requirement from paper copy to electronically, the DEEP Engineering Unit has decided to extend the due date of project/solicitation #DEPA00029000104-Devils Hopyard to April 15, 2020 at 2:00pm Local time.
- Addendum #3 - 4/6/20 - Sealed Bids shall be sent electronically to the Engineering Unit via e-mail: joseph.buyonje@ct.gov
All bids received prior to the date and time of bid opening will be tabulated by the Engineering Unit and the bid tabulation list posted on BizNet within three (3) business days. All Bid Forms shall be shared with all bidders.
- Addendum #2 - Posting Q & A (3/20/20)
- Addendum #1 - Closing date was extended to 4/8/20
|
|
|
Contact Name |
Joseph Buyonje |
E-Mail |
Joseph.buyonje@ct.gov |
Phone |
(860) 424-4121 |
FAX |
(860) 344-2560 |
WebSite |
www.ct.gov/deep |
|
Additional Description |
Bridge E118 (DOT #06323) dates to 1970 and is located in Devil's Hopyard State Park, East Haddam, CT. The bridge carries Loop trail over Eight Mile River, a national wild and scenic river. The bridge is an aesthetic covered bridge which is very popular and used by hikers (recreating public) for recreational purposes along loop trail. Per the 2016 bridge inspection report, the bridge was found to be in overall poor condition and in need of the replacement of its superstructure with also minor substructure work needed. Replacement superstructure type to be a wooden covered bridge so as to preserve the current aesthetic view. Superstructure replacement work will ensure the safe use of the bridge by the recreating public. Specific work includes the demolition of the existing superstructure, restoration of existing W8 steel beams and base plates and replacement of the superstructure. Work also includes clearing in designated areas, protecting existing planting to remain, stripping and stockpiling of topsoil, site landscaping, site grading and installation of all erosion and sediment control measures.
It is the goal of DEEP Engineering and Support Services to replace the existing bridge superstructure with a new wooden covered bridge superstructure so as to preserve the current aesthetic view of the bridge. |
|
Documents |
|
|
|
Conference Date |
3/5/2020 10:00:00 AM |
Address |
366 Hopyard Rd East Haddam, CT 06423 |
Instructions |
Devil's Hopyard State Park
366 Hopyard Rd, East Haddam, CT 06423
|
Map Link |
|
|