Current User: Home Biznet Menu Log In/Out
SCP Solicitation Details
State Contracting Portal Solicitation Details

Organization Branford, Town of
Project/Solicitation # BRADLEY AND HEMLOCK PUMP STATION PIPING MODIFICATI
Solicitation Type Invitation to Bid
Due Date 11/21/2019
Includes SBE/MBE Requirements NO
Qualified Partnership NO
Summary BRADLEY AND HEMLOCK PUMP STATION PIPING MODIFICATIONS
Addenda
  • ADDENDUM NO. 2 TO CONTRACT DOCUMENTS FOR TOWN OF BRANFORD, CONNECTICUT BRADLEY & HEMLOCK PUMP STATION PIPING MODIFICATIONS CONTRACT NO. 41 NOVEMBER 14, 2019 GENERAL See attached concrete entrance landing detail at the Bradley Pump Station that was referenced in Question 8 of Addendum No. 1. Town Engineer Town of Branford
  • ADDENDUM NO. 1 TO CONTRACT DOCUMENTS FOR TOWN OF BRANFORD, CONNECTICUT BRADLEY & HEMLOCK PUMP STATION PIPING MODIFICATIONS CONTRACT NO. 41 NOVEMBER 13, 2019 GENERAL The following changes and additional information are hereby made part of the Contract Documents: QUESTIONS AND ANSWERS RECEIVED THROUGH DATE Question 1: How long is the existing force main pipe for the Bradley Pump Station? Answer 1: Approximately 350 LF Question 2: How long and what diameter is the existing force main for the Hemlock Pump Station? Answer 2: Approximately 3,000 LF 8” dia. Question 3: The photo on Figure #4 of the Bradley Pump Station indicates the underground electrical service may be close to the new underground force main pipe. Can a drawing be provided of the location of the existing underground electrical service location? Answer 3: No information is available. Question 4: The photo on Figure #4 of the Bradley Pump Station indicates the new underground force main will pass under an existing paved sidewalk and an existing chain link fence. Is the contractor responsible for costs to restore the paved sidewalk and fence back to the existing condition? Answer 4: Yes Question 5: The photo on Figure #2 of the Bradley Pump Station indicates the existing flow meter is to be demolished. Is the contractor responsible for disconnecting the existing electrical and signal wiring from the existing flow meter? Answer 5: Yes Question 6: Figure #5 of the Bradley Pump Station indicates the new flow meter is to be installed on the pipeline. We have the following questions on the flow meter: Question 6a: Is the contractor responsible for providing the conduit and wiring for the new flowmeter? Answer 6a: No. Question 6b: Is the contractor responsible for the programming of the new flow meter? Answer 6b: No. Question 6c: Is the contractor responsible for providing factory start up services for the new flow meter? Answer 6c: No. Question 7: In specification section 01030 subsection 1.06 H on page 01030-3 it is noted that the paint and concrete at the Bradley Pump Station may contain PCBs. Is there any PCB paint at the Hemlock Pump Station? Answer 7: No. Question 8: The photo on Figure #4 of the Bradley Pump Station indicates the existing underground force main pipe is coming out of the building on the right front side of the building, but after our field inspection we found that the existing force main pipe is coming out of the building on the left hand front side, just under the entry doorway into the building. To remove the existing force main pipe the existing 5’ x 3’ concrete entrance landing will have to be demolished. Will we have to replace the concrete entrance landing? If we do have to replace the pad can a detail be provided on the replacement pad? Answer 8: Yes. See attached detail. Question 9: Will building permit fees be waived? Answer 9: Yes Question 10: Has there been an extensive hazardous materials survey? Answer 10: No Question 11: Is the GC responsible for removing all noted hazardous materials or only those impacted by new work? Answer 11: Only those impacted by new work. Question 12: Is there an existing bypass connection? Answer 12: There is a bypass connection at the Hemlock Pump Station, but not at the Bradley Pump Station. Question 13: During bypass pumping, does the GC need to have 24-hour supervision? Answer 13: No, but it must be operational for 24 hours as specified and alarms shall be monitored and addressed 24 hours per day, 7 days a week. Question 14: Does the new interior piping need to be painted? Is there a specification? Answer 14: The new interior pipe shall be painted with two coats of Tnemec Series 66HS Hi-Build Epoxoline as specified in Section 15100-2.01-A-2. Question 15: In reference to the contract completion time, the lead times on the valves, in particular the surge relief valve may be extensive. Will you consider extending the completion date? Answer 15: Yes, if sufficient evidence can be provided. Question 16: Is there a common influent manhole that we can suck out of for bypass pumping? What is the depth of the manhole? How long are the force mains before they turn to gravity? What is the diameter of each force main? Answer 16: There is a common manhole or wet well at each station to pump from for bypass piping. The depth of the manhole at the Bradley Pump Station is approximately 16 feet 6 inches to the flowline, and the depth of the manhole at the Hemlock Pump Station is approximately 15 feet. The Bradley force main is 8 inches in diameter and is approximately 350 feet long. The Hemlock force main is 8 inches in diameter and is approximately 3,000 feet long. Question 17: In reference to Section 01030 1.02 A.5, is there a site drawing for the Bradley Pump Station showing all the existing underground utilities? Answer 17: No. Question 18: In reference to Figure 2, it appears that the

Contact Name John Hoefferle
E-Mail jhoefferle@branford-ct.gov
Phone (203) 315-0606
FAX
WebSite www.branford-ct.gov

Additional Description The Town of Branford, Connecticut, hereby gives notice that sealed Bids will be received for the Bradley and Hemlock Pump Station Piping Modifications. The work at the Bradley Pump Station includes, but is not limited to, the replacement of approximately 30 LF of 8-inch cast iron force main with ductile iron pipe and fittings from inside the pumping station to an area outside the pump station. A sewage surge relief valve, gate valves, and piping will be installed at the Hemlock Pumping Station. The Work under the proposed Contract shall commence within 60 days after the date set forth in the Notice to Proceed and shall be completed within 195 days after start of Work. The Purchasing Clerk for the Town of Branford, Connecticut will receive sealed bids until 11:00 a.m. Local Time on November 21, 2019, at the Finance Office, Town Hall, 1019 Main Street, Branford Connecticut 06405, at which time they will be publicly opened and read aloud. Plans and specifications for this project will be available for download at the Town of Branford website and at the CT DAS website. A printed set of plans and specifications are available for review during business hours after October 29, 2019, at the Town Hall Engineer’s Office 1019 Main Street Branford, CT 06405. No Bid shall be withdrawn for a period of 90 days after the opening of Bids without consent of Owner. The Owner reserves the right to reject any and all Bids, waive informalities or minor defects in bidding or to accept the Bid or Bids, which best serve the interests of Owner.

Documents
Hit Counter 21,025,373